The following company details, goals and timelines describe a hypothetical project scenario developed for learning and concept work. No real-world implementation has been verified. Actual baselines, budgets and legal conditions would need to be established before implementation.
01 · Initial situation
A fictional medium-sized company with 50–250 employees handles customer enquiries via service email, telephone and CRM. A team of 5–20 employees answers many similar standard questions but must search across documents and systems for more complex cases. The existing infrastructure uses Microsoft 365, shared service mailboxes and document storage.
The proposed approach aims to reduce repetitive work while ensuring expert review of complex or sensitive responses. AI initially supports employees through classification, summarisation and suggested replies – it is not authorised to send sensitive replies independently during the pilot.
02 · Goals & success criteria
| Goal | Metric | Evaluation |
|---|---|---|
| Speed up handling | Time to first qualified draft | Define target after baseline; illustrative hypothesis: 24 h → 2 h for standard cases |
| Maintain quality | Factually correct answers in sample reviews | Launch only after meeting defined quality levels and documented approvals |
| Reduce staff workload | Time per case / adoption feedback | Measurable improvement without shifting errors to downstream processes |
Key distinction: A short AI response draft does not necessarily mean a short resolution time. Both drafting time and actual time to resolve a case are measured alongside quality indicators.
03 · Scope, technology & data
In scope for the pilot
- Automatically classify incoming standard enquiries by topic and priority.
- Summarise longer email threads.
- Produce AI-assisted reply suggestions from approved knowledge documents.
- Integrate into a controlled workflow requiring human approval.
Out of scope for the pilot
- Autonomous sending of legally binding or sensitive responses.
- Automated decisions about reimbursements, contracts or high-impact complaints.
- Complete replacement of telephone service or CRM.
Data & protective measures
Before launch, the types of enquiries, storage locations, data quality and access permissions are documented. Personal data should be minimised and pseudonymised or anonymised where appropriate. Role-based access, deletion rules, test datasets and subject-matter quality reviews are required. Legal bases, processing agreements, any need for a data protection impact assessment and provider terms must be checked with the data protection officer before implementation.
04 · Team, responsibilities & RACI
The project needs an executive sponsor, AI project manager, customer service owner, IT/information security and data protection. RACI distinguishes Responsible (performing), Accountable (ultimately accountable), Consulted (advisory) and Informed (kept informed).
| Work package | Executive management | AI PM | Service manager | IT | Data protection officer |
|---|---|---|---|---|---|
| Project mandate & budget | A | R | C | C | I |
| Use cases & success criteria | I | A | R | C | C |
| Technical integration | I | A | C | R | C |
| Data protection review | A | R | C | C | C |
| Pilot sign-off | A | R | R | C | C |
| Ongoing quality assurance | I | A | R | C | C |
Simplified RACI example. Before implementation, responsibility for binding decisions must be specified for every activity. The data protection officer provides expert input; responsibility for processing decisions remains with the organisation acting as controller.
05 · Implementation & timeline
Recommendation: Pilot first, rather than a big-bang launch. The following twelve weeks are a planning hypothesis, not a promised project duration.
| Phase | Period | Deliverable |
|---|---|---|
| Analysis | Weeks 1–2 | Use-case list, baseline, data inventory, risk assessment, approvals |
| Prototype | Weeks 3–4 | Classification and reply drafts using anonymised examples |
| Integration | Weeks 5–7 | Access controls, knowledge sources, interfaces, test logs |
| Pilot | Weeks 8–10 | Tests with a defined staff group, training, reviews and error analysis |
| Evaluation | Weeks 11–12 | KPI comparison; management decision to expand, adapt or stop |
A Kanban board tracks requirements, technical tasks and defects. Results are demonstrated in short two-week cycles, risks are updated and employee feedback is considered.
06 · Five principal risks
| Risk | Impact | Mitigation |
|---|---|---|
| Incorrect or fabricated replies | Incorrect information to customers | Approved sources, sampling, human sign-off and an error log |
| Unlawful data processing | Privacy and trust risks | Data inventory, DPO review, least privilege and contract checks |
| Weak CRM/email integration | Manual hand-offs, delays and errors | API tests, limited pilot, fallback process |
| Low adoption | Low usage despite investment | Early employee involvement, training and feedback loops |
| Underestimated effort | Budget and schedule risk | Clear scope, milestones, cost controls and stop/go criteria |
A real risk register should additionally record owners, likelihood, impact, effectiveness of controls and residual risk for each risk. These cannot be quantified reliably without actual project data.
07 · KPIs & reporting
- Handling time: Median time from receipt to resolution.
- First response time: Time to the first qualified response, broken down by enquiry type.
- Answer quality: Share of error-free responses in a documented sample.
- AI adoption rate: Share of suitable cases in which staff use the assistant.
- Customer satisfaction: CSAT or comparable feedback before and after the pilot.
The baseline is collected before the pilot. Results are analysed by channel and enquiry type. Weekly pilot reporting covers usage, quality, error types and new risks; a management report with a go/no-go recommendation follows at the end.
08 · Operations, maintenance & sign-off
In regular operations, a technical owner is needed for interfaces and permissions, a business owner for knowledge content and a project owner for KPIs, changes and approvals. Documents must be maintained, new reply patterns tested and security incidents handled in a structured manner.
Go/no-go criteria
- Privacy and security requirements are documented and checked.
- Answer quality meets the pre-agreed threshold.
- Manual case handling remains possible at all times.
- Employees understand limitations, approval rules and escalation paths.
- Business value is plausible based on reliable baseline data.
AI should support staff with standardisable tasks, not replace professional accountability. Only measurable results from a controlled pilot can determine whether a broader rollout makes sense.